CCGT Project Progress
The Romanian Energy Regulatory Authority (ANRE) issued the Set-Up Permit No 1167 to build a new energy capacity;
On October 31, 2016, a works contract was concluded between S.N.G.N. Romgaz S.A. and the consortium of Duro Felguera S.A. and S.C. Romelectro S.A. referring to a turn-key contract for of a new, combined cycle gas turbine power plant, including engineering, supply of equipment, performance of works and commissioning;
The Environmental Agreement for the project was obtained, issued by the Environmental Protection Agency of Mures;
In accordance with the Government Decision 1096/ 2013, the Application Documents for PNI (National Investment Plan) Financing were submitted to the Ministry of Energy on December 6, 2016;
The Ministry of Energy approved the PNI Financing Application on January, 18, 2017;
On March 14, 2017, the project kick-off meeting was held between the representatives of Romgaz and Duro Felguera and Romelectro, respectively, at the premises of S.P.E.E. Iernut;
The contractor concluded the contracts for the supply of the main equipment (gas turbines, steam turbines, heat recovery steam generators) from the manufacturer (General Electric);
On October 17, 2017, the Construction Permit to build a new power plant was issued;
The PNI Grant Agreement was signed on December 7, 2017;
The first request for reimbursement was submitted to the Ministry of Energy on December 14, 2017;
Indirect foundation (foundation piles) works were completed and direct foundation works are in progress;
The main equipment was supplied (gas turbines, generators, auxiliary installation, fastening and anchoring systems, connecting pipelines and elements of the heat recovery steam generators)